<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Pump Station PS-07 - Construction</Name>
  <Title>Pump Station PS-07 - Construction</Title>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2027-01-04T08:00:00</StartDate>
  <CalendarUID>1</CalendarUID>
  <MinutesPerDay>480</MinutesPerDay>
  <MinutesPerWeek>2400</MinutesPerWeek>
  <DaysPerMonth>20</DaysPerMonth>
  <CurrencyCode>USD</CurrencyCode>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>Standard 5-Day (Site)</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay><DayType>1</DayType><DayWorking>0</DayWorking></WeekDay>
        <WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>7</DayType><DayWorking>0</DayWorking></WeekDay>
      </WeekDays>
      <Exceptions>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-03-13T00:00:00</FromDate><ToDate>2027-03-13T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Worked Saturday</Name>
          <Type>1</Type>
          <DayWorking>1</DayWorking>
          <WorkingTimes><WorkingTime><FromTime>08:00:00</FromTime><ToTime>12:00:00</ToTime></WorkingTime><WorkingTime><FromTime>13:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-03-26T00:00:00</FromDate><ToDate>2027-03-26T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-03-29T00:00:00</FromDate><ToDate>2027-03-29T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-05-03T00:00:00</FromDate><ToDate>2027-05-03T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-05-31T00:00:00</FromDate><ToDate>2027-05-31T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-08-30T00:00:00</FromDate><ToDate>2027-08-30T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-12-27T00:00:00</FromDate><ToDate>2027-12-27T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-12-28T00:00:00</FromDate><ToDate>2027-12-28T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
      </Exceptions>
    </Calendar>
    <Calendar>
      <UID>2</UID>
      <Name>7-Day Continuous 10h (Dewatering/Curing)</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay><DayType>1</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>2</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>3</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>4</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>5</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>6</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
        <WeekDay><DayType>7</DayType><DayWorking>1</DayWorking><WorkingTimes><WorkingTime><FromTime>07:00:00</FromTime><ToTime>17:00:00</ToTime></WorkingTime></WorkingTimes></WeekDay>
      </WeekDays>
      <Exceptions>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod><FromDate>2027-12-25T00:00:00</FromDate><ToDate>2027-12-25T23:59:00</ToDate></TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Public holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
      </Exceptions>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task><UID>0</UID><ID>0</ID><Name>Pump Station PS-07 - Construction</Name><OutlineLevel>0</OutlineLevel><Summary>1</Summary><Start>2027-01-04T08:00:00</Start><Finish>2027-07-06T17:00:00</Finish><Cost>1304000</Cost></Task>
    <Task><UID>1</UID><ID>1</ID><Name>Engineering &amp; Procurement</Name><WBS>PS-07.1</WBS><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Cost>659000</Cost></Task>
    <Task><UID>2</UID><ID>2</ID><Name>Notice to proceed</Name><WBS>A1000</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>1</Milestone><Start>2027-01-04T08:00:00</Start><Finish>2027-01-04T08:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost></Task>
    <Task><UID>3</UID><ID>3</ID><Name>Detailed design</Name><WBS>A1010</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-01-04T08:00:00</Start><Finish>2027-01-29T17:00:00</Finish><Duration>PT160H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>85000</FixedCost><Cost>85000</Cost><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>4</UID><ID>4</ID><Name>Design review &amp; approval</Name><WBS>A1020</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-01T08:00:00</Start><Finish>2027-02-05T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>3</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>5</UID><ID>5</ID><Name>Pump purchase order &amp; submittals</Name><WBS>A1030</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-08T08:00:00</Start><Finish>2027-02-19T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>6</UID><ID>6</ID><Name>Manufacture pumps</Name><WBS>A1035</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-22T08:00:00</Start><Finish>2027-04-19T17:00:00</Finish><Duration>PT320H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>420000</FixedCost><Cost>420000</Cost><PredecessorLink><PredecessorUID>5</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>7</UID><ID>7</ID><Name>Factory test &amp; delivery of pumps</Name><WBS>A1038</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-04-20T08:00:00</Start><Finish>2027-05-04T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>18000</FixedCost><Cost>18000</Cost><PredecessorLink><PredecessorUID>6</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>8</UID><ID>8</ID><Name>Procure pipework &amp; valves</Name><WBS>A1040</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-22T08:00:00</Start><Finish>2027-04-05T17:00:00</Finish><Duration>PT240H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>136000</FixedCost><Cost>136000</Cost><PredecessorLink><PredecessorUID>5</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>9</UID><ID>9</ID><Name>Site Works</Name><WBS>PS-07.2</WBS><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Cost>205000</Cost></Task>
    <Task><UID>10</UID><ID>10</ID><Name>Site mobilisation</Name><WBS>A1100</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-01-11T08:00:00</Start><Finish>2027-01-15T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>4</ConstraintType><ConstraintDate>2027-01-11T08:00:00</ConstraintDate><FixedCost>22000</FixedCost><Cost>22000</Cost><PredecessorLink><PredecessorUID>2</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>11</UID><ID>11</ID><Name>Install temporary power</Name><WBS>A1105</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-01-18T08:00:00</Start><Finish>2027-01-19T17:00:00</Finish><Duration>PT16H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>30000</FixedCost><Cost>30000</Cost><PredecessorLink><PredecessorUID>10</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>12</UID><ID>12</ID><Name>Dewatering</Name><WBS>A1110</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-01-20T07:00:00</Start><Finish>2027-01-29T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>2</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>48000</FixedCost><Cost>48000</Cost><PredecessorLink><PredecessorUID>11</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>13</UID><ID>13</ID><Name>Excavation</Name><WBS>A1120</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-01T08:00:00</Start><Finish>2027-02-16T17:00:00</Finish><Duration>PT96H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>64000</FixedCost><Cost>64000</Cost><PredecessorLink><PredecessorUID>12</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>14</UID><ID>14</ID><Name>Backfill around structure</Name><WBS>A1230</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-04-13T08:00:00</Start><Finish>2027-04-22T17:00:00</Finish><Duration>PT64H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>21</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>15</UID><ID>15</ID><Name>Lay incoming power cable</Name><WBS>A1240</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-04-23T08:00:00</Start><Finish>2027-04-29T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>26000</FixedCost><Cost>26000</Cost><PredecessorLink><PredecessorUID>14</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>16</UID><ID>16</ID><Name>Demobilise &amp; reinstate site</Name><WBS>A1350</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-06-30T08:00:00</Start><Finish>2027-07-06T17:00:00</Finish><Duration>PT40H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>15000</FixedCost><Cost>15000</Cost><PredecessorLink><PredecessorUID>27</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>17</UID><ID>17</ID><Name>Civil Structure</Name><WBS>PS-07.3</WBS><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Cost>248000</Cost></Task>
    <Task><UID>18</UID><ID>18</ID><Name>Blinding &amp; formwork</Name><WBS>A1130</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-17T08:00:00</Start><Finish>2027-02-24T17:00:00</Finish><Duration>PT48H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>13</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>4</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>19</UID><ID>19</ID><Name>Pour base slab</Name><WBS>A1200</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-25T08:00:00</Start><Finish>2027-02-26T17:00:00</Finish><Duration>PT16H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>38000</FixedCost><Cost>38000</Cost><PredecessorLink><PredecessorUID>18</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>20</UID><ID>20</ID><Name>Cure base slab</Name><WBS>A1210</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-02-27T07:00:00</Start><Finish>2027-03-05T17:00:00</Finish><Duration>PT56H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>2</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>19</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>21</UID><ID>21</ID><Name>Walls &amp; roof structure</Name><WBS>A1220</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-03-08T08:00:00</Start><Finish>2027-04-12T17:00:00</Finish><Duration>PT200H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>210000</FixedCost><Cost>210000</Cost><PredecessorLink><PredecessorUID>20</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>22</UID><ID>22</ID><Name>M&amp;E Installation &amp; Commissioning</Name><WBS>PS-07.4</WBS><OutlineLevel>1</OutlineLevel><Summary>1</Summary><Cost>192000</Cost></Task>
    <Task><UID>23</UID><ID>23</ID><Name>Install pumps</Name><WBS>A1300</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-05-05T08:00:00</Start><Finish>2027-05-18T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>54000</FixedCost><Cost>54000</Cost><PredecessorLink><PredecessorUID>7</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>21</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>24</UID><ID>24</ID><Name>Install pipework</Name><WBS>A1310</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-05-19T08:00:00</Start><Finish>2027-06-09T17:00:00</Finish><Duration>PT120H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>23</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>8</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>25</UID><ID>25</ID><Name>Electrical &amp; controls</Name><WBS>A1320</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-05-19T08:00:00</Start><Finish>2027-06-14T17:00:00</Finish><Duration>PT144H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>97000</FixedCost><Cost>97000</Cost><PredecessorLink><PredecessorUID>23</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>26</UID><ID>26</ID><Name>Energise permanent supply</Name><WBS>A1325</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-06-15T08:00:00</Start><Finish>2027-06-15T17:00:00</Finish><Duration>PT8H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><PredecessorLink><PredecessorUID>25</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>15</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>27</UID><ID>27</ID><Name>Testing &amp; commissioning</Name><WBS>A1330</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>0</Milestone><Start>2027-06-16T08:00:00</Start><Finish>2027-06-29T17:00:00</Finish><Duration>PT80H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>41000</FixedCost><Cost>41000</Cost><PredecessorLink><PredecessorUID>24</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink><PredecessorLink><PredecessorUID>26</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
    <Task><UID>28</UID><ID>28</ID><Name>Mechanical completion</Name><WBS>A1340</WBS><Type>1</Type><OutlineLevel>2</OutlineLevel><Summary>0</Summary><Milestone>1</Milestone><Start>2027-07-06T17:00:00</Start><Finish>2027-07-06T17:00:00</Finish><Duration>PT0H0M0S</Duration><DurationFormat>7</DurationFormat><CalendarUID>-1</CalendarUID><ConstraintType>0</ConstraintType><FixedCost>0</FixedCost><Cost>0</Cost><Deadline>2027-09-30T17:00:00</Deadline><PredecessorLink><PredecessorUID>16</PredecessorUID><Type>1</Type><LinkLag>0</LinkLag><LagFormat>7</LagFormat></PredecessorLink></Task>
  </Tasks>
</Project>